Commercial concrete & structural steel · The Carolinas

We build the part of the building that holds the building up.

Corrigan self-performs structural concrete and steel — tilt-up, cast-in-place, erection — with our own crews, our own iron, and a recordable rate general contractors ask us to explain. Since 1987.

Corrigan Structural Group

Founded
1987 — Charlotte, NC
Self-performed
Concrete · steel erection · rebar
Field crews
14 crews / 160 tradespeople
EMR
0.71 (3-year average)
Bonding
Single $40M / aggregate $120M

Current capacity

Concrete placed / yr
~90,000 CY
Steel erected / yr
~6,500 tons
Typical contract
$1.5M – $30M
Now bidding
Q4 2026 starts

Selected work

Three jobs that describe the company.

Riverbend Logistics Hub

410,000 SF

Tilt-up — 74 panels

Concrete
18,400 CY
Schedule
Structure topped out 9 days early

Gaston Medical Pavilion

160,000 SF

Cast-in-place frame, 5 stories

Concrete
11,200 CY
Note
Occupied-campus logistics, zero disruptions logged

Piedmont Forge Works

2,100 tons

Steel erection + mezzanines

Crane days
61
Note
Design-assist from 60% drawings

Full project list with owner references available on request — we'd rather you call our last three clients than read our copy.

How we work

Self-performed, or we don't sign.

Corrigan doesn't broker structural work to subs and mark it up. The crews on your site are our payroll, our superintendents, our safety program. That's why the schedule holds: the people who promised it are the people pouring it.

Bring us drawings at sixty percent and we'll flag the constructability problems while they're still eraser-fixable. Bring them finished and we'll give you a number that doesn't move without a scope change.

Read about the company

Safety record

EMR
0.71
TRIR
1.2 (2025)
OSHA citations
0 in last 5 years

Bidding Q4 starts now.

Send drawings and a schedule. You'll have a call back from an estimator — not an inbox autoreply — within one business day.